Have you already considered whether the wall will have openings (doors, windows)? What they said is fine, but here's an important detail: once you have the total cubic meters, subtract the volume of those openings before doing the final division. Because if you don't, you're going to end up buying extra material for no reason. Plus, always add an extra 10-15% for breakage and adjustments during construction - don't count on everything going perfectly 😅

Pescador asker Oh right, I hadn't thought that through properly. Thanks for the tip about the openings and the extra percentage.

You need to measure the wall's total height, length, and thickness, multiply those to get cubic meters, and then divide by the volume that one unit of material takes up (brick, block, stone) depending on the mortar joints you use. The most important thing is having the design and specifications crystal clear, because a measurement error will leave you short or with material going to waste.